Introduction
The Supreme Court has held that bidders cannot  be disqualified for non-submission of a Joint Venture agreement when such submission  is not expressly mandated by the tender terms. The Court held that tender  conditions must be clear and unambiguous and that courts must not read  additional requirements into contractual clauses.
					
						Background
The Appellant, Maha Mineral Mining & Beneficiation  Pvt. Ltd., had participated in a tender floated by the Respondent for  beneficiation and logistics of coal for the Shree Singaji Thermal Power  Project. The Appellant sought to rely on past experience executed through a  previous consortium and submitted a work execution certificate from the  Maharashtra State Mining Corporation, which recorded the Appellant’s 45 percent  share in the JV, Hind Maha Mineral LLP, and specified the relevant JV agreement  date as 2nd December 2019. However, the Tender Evaluation Committee rejected  the Appellant’s bid, citing failure to submit the JV agreement to prove its  shareholding under Clause 5(D) of the Notice Inviting Tender (NIT). The High  Court upheld the disqualification and further held that even if the JV agreement  had been submitted, the Appellant would have stood disqualified under Clause  5(B) for lack of spare washery capacity.
Aggrieved by the High Court’s findings and the  manner in which new grounds of disqualification were introduced at the stage of  final hearing, the Appellant approached the Supreme Court by way of Special  Leave Petition.
					
						Supreme Court’s  Findings
The Supreme Court examined the disqualification  of the Appellant under Clause 5(D) of the NIT and found that the rejection was  not supported by the tender terms. It held that Clause 5(D) did not require  mandatory submission of the Joint Venture agreement. The Appellant had  submitted a work execution certificate issued by the Maharashtra State Mining  Corporation, which clearly stated that the Appellant held a 45 percent share in  the consortium and had completed similar work. The Court noted that the Tender  Evaluation Committee failed to exercise its discretion under Clause 8.8 of the  NIT, which permitted it to seek clarifications or additional documents,  especially when there was no dispute about the authenticity of the certificate.  It also rejected the argument that the Appellant had acted with mala fides or  suppressed documents, as all versions of the JV agreement showed the same  proportionate share and were consistent with the certificate. The Court further  held that the High Court was not justified in introducing a fresh ground of  disqualification under Clause 5(B) without giving the Appellant a proper  opportunity to respond, especially when that ground had not been considered by  the Tender Committee at all.
					
						Conclusion
The Supreme Court held that the Appellant’s  disqualification for failure to submit the JV agreement was arbitrary and  contrary to the express terms of the NIT. It emphasised that tender conditions  must be applied strictly and that bidders cannot be disqualified for not  complying with a requirement that is not clearly stated. The Court set aside  the findings of the High Court and the rejection under Clause 5(D). However, it  remanded the question of disqualification under Clause 5(B) for fresh  consideration by the High Court as that issue involved disputed facts and had  not been adequately addressed in the earlier proceedings. The appeal was  accordingly partly allowed1.
					
By - Chaitanyaa Bhandarkar
Top
