Introduction
In a recent ruling,  the Supreme Court reaffirmed the settled principles governing public  procurement thereby quashing a Calcutta High Court Division Bench judgment that  had permitted post-bid rectification of a financial quote in an e-tender. The  Court held that permitting such modifications after the opening of bids  undermines the sanctity transparency and finality of the tender process and  cannot be justified on grounds of an     “inadvertent error.”.
					
						Background
The matter pertained  to a public e-tender floated by the West Bengal Public Works (Roads)  Directorate for the collection of Road User Fees (RUF) at a toll plaza.  Mandeepa Enterprises, one of the bidders, quoted Rs. 9,72,999 in its financial  bid for a contract period of 1095 days. This was interpreted by the tendering  authority as the total bid value. Prakash Asphaltings, whose bid stood at Rs.  91.19 crores, was declared the H1 bidder.
Mandeepa Enterprises,  however, claimed that its figure was a per day rate and that it had  inadvertently failed to multiply it by 1095. On that basis, it contended that  its bid was in fact over Rs. 106 crores and thus higher than that of Prakash  Asphaltings. It sought to justify this by relying on Clause 5B(v) of the tender  terms, which allowed for clarifications to be sought. The tendering authority  rejected this contention, citing Clause 4(g), which specifically prohibited any  modification of the BOQ after submission.
Mandeepa challenged  this decision by filing a writ petition before a Single Judge of the Calcutta  High Court. The Single Judge dismissed the petition, upholding the finality of  the submitted bid and the authority    ’s interpretation. Mandeepa then filed an intra-court  appeal before the Division Bench. The Division Bench held that the instant case  is not one of modification or amendment of the bid, but a case where the bidder  seeks to explain the rate quoted in the BOQ Form. Based on that finding, the  Division Bench allowed the appeal, permitted Mandeepa    ’s explanation to be  considered and directed the tendering authority to re-evaluate the financial  bids accordingly. This order was passed without issuing notice to Prakash  Asphaltings, the successful H1 bidder. Aggrieved, Prakash Asphaltings  approached the Hon    ’ble Supreme Court.
					
						Supreme Court    ’s  Findings
The Supreme Court  held that Clause 5B(v), which permits clarifications in respect of bids, does  not override Clause 4(g), which mandates that no change whatsoever be made to  the BOQ template after submission. Mandeepa    ’s  contention that the quoted amount was on a per-day basis ran contrary to the  plain language of the BOQ, which required a total amount for 1095 days to be  quoted in figures and in words. There was no ambiguity that called for  clarification. The Court was critical of Mandeepa    ’s     “very  casual approach” and held that the bidder     “cannot be permitted  to blow hot and cold”. Permitting such a change post bid submission would  compromise fairness, transparency, and the level playing field among bidders.  The Court rejected the High Court    ’s characterization that Mandeepa was not amending its  bid and held that the Division Bench fell in error in accepting the explanation  of Mandeepa Enterprises as a mere clarification and that this approach would  set a bad precedent.
					
						Conclusion
The decision  reinforces the settled principle that tender conditions are sacrosanct and  cannot be relaxed or overridden by post-bid clarifications, especially when  they pertain to financial offers. Even a bona fide error is not sufficient  ground to permit rectification once bids are opened. The ruling strengthens the  authority of earlier precedents such as Patel Engineering Ltd. v. Union of  India, (2012) 11 SCC 257, Afcons Infrastructure Ltd. v. Nagpur Metro Rail  Corporation Ltd., (2016) 16 SCC 818, Jagdish Mandal v. State of Orissa, (2007)  14 SCC 517 and Reliance Energy Ltd. v. MSRDC, (2007) 8 SCC 1, each of which  reaffirm the legal position that procedural fairness, equal treatment of  bidders and strict compliance with the terms of the tender are essential to  maintaining the integrity of public procurement. The Supreme Court    ’s  ruling in Prakash Asphaltings affirms that transparency and fairness in the  bidding process are paramount and cannot be compromised by subsequent  justifications, however inadvertent or well-intentioned the error may be1.
					
By - Chaitanyaa Bhandarkar
Top
