Introduction
In a recent judgment, the  Division Bench of the Bombay High Court directed Maharashtra State Electricity  Distribution Co. Ltd. (MSEDCL) to acquire the land of the Petitioners, which  was taken over more than 37 years prior to the filing of the Petition, under  the provisions of the 2013 Land Acquisition Act, and to pay compensation to the  Petitioner within a period of three months.
			
				Background and Procedural History
In a Writ Petition filed  before the Bombay High Court in the year 2022, the Petitioners claimed to be  successors in title of a certain landowner whose property had been occupied by  the Maharashtra State Electricity Board (MSEB) since 1984, as revealed by a  survey conducted in 2019 at the instance of the Petitioners. The record showed  that MSEDCL had erected an electricity substation on the subject plot. It was  also revealed that MSEB, the predecessor of Maharashtra State Electricity  Distribution Co. Ltd. (MSEDCL), had applied to the State Government to acquire  the said plot by following the procedure under Sections 128 and 129 of the  Maharashtra Regional and Town Planning (MRTP) Act. However, the proceedings for  the acquisition of the land had not been conducted. The possession of the land  was subsequently transferred to MSEDCL. Consequently, the Petition was filed,  accusing MSEDCL of being an unlawful encroacher and usurper of the subject  land. The Petitioners contended that the only correct redress was that the land  acquisition procedure under the then applicable law, namely, the Right to Fair  Compensation and Transparency in Land Acquisition, Rehabilitation, and  Resettlement Act, 2013, should be followed, and the Petitioners should be  awarded compensation.
			
				Contentions of the state and MSEDCL
The  Respondents opposed the Petition on the ground of delays and laches, that is,  the Petition was filed after a delay of nearly 40 years from the date of  possession by the Maharashtra State Electricity Board (MSEB). It was also contended  that the Electricity Law, that is, the Electricity Act and regulations made  thereunder, have waded into the domain of the Land Acquisition Act. The  Electricity Act stipulates the formation of an Electricity Code. The 2021  Regulations under the Electricity Act are a self-contained code and are made  under Section 50 of the Electricity Act. It was contended on behalf of the  Respondents that this would deal with all matters of rights and obligations  connected with the supply of electricity. It was further contended by the  Respondents that by virtue of Regulation 6.5 of the 2021 Regulations, the  Petitioners, at best would be allowed a lease rental of Rs. 1 per annum.
			
				High Court’s Decision
In  addressing the issue of delay and laches, the Division Bench of the Bombay High  Court applied relevant principles to the case. The Court found that dismissing  the Petitioners' Writ Petition solely based on delay would be unjust. It also  noted that considering the Petition on its merits would not disadvantage  Maharashtra State Electricity Distribution Co. Ltd. (MSEDCL) and the State. The  Court identified the main argument that electricity law supersedes land  acquisition laws as misconceived. The Court observed that there was no dispute  over the identity of the Subject Land or its possession history. It was evident  that the State had not chosen a specific legislation for land acquisition and  was aware of its obligation to pay compensation yet failed to do so. The Court  concluded that the Petitioners were entitled to compensation for the land  acquired by MSEDCL. The Court directed the Collector, to calculate compensation  under the 2013 Land Acquisition Act within three months and ensure its payment  by MSEDCL. This decision ensures justice is served without causing undue harm  to any party involved.1
			
By - Chaitanyaa Bhandarkar
Top
