The Hon’ble Supreme Court vide its  judgment1 dated November 07, 2022, has recalled its previous orders2 granting relief on an interim application by a real estate developer in case  concerning Amrapali Group whereby the interest was capped at 8% simple interest  per annum on the outstanding premium and dues to be realised by Noida and  Greater Noida on the land leased to private developer. Further the Hon’ble  Court in clarification stated that the intention was to cap the rate of  interest to the rate charged by the Bank and the cut of date for calculation of  the rate of interest was from 01.01.2010. The arrears before the abovementioned  dates were to be paid as per the terms of the agreement.
It is relevant to consider the context in the  which the order of the Hon’ble Supreme Court was passed. The Court was hearing  the plea of the aggrieved homebuyers in the projects of Amrapali Group of  Companies, wherein, an interim application was filed by the builder in the name  of Ace Group claiming relief on similar lines as requested by the flat buyer of  Amrapali Group. Ace group requested the Court for general reduction in rate of  interest charged by Noida and Greater Noida authorities. The plea of the Ace  group was that the authorities are levying excessive and penal interest in  contrast to the prevailing financial market scenario. It was submitted that the  rate charged ranges from 15-23% per annum with half yearly compounding. It is  also the case that land allotted is sometimes encumbered and disputed and this  distress has further resulted into crisis with the Covid outbreak and post  covid situations. It has become almost impossible for the developers to bear  the brunt and resultantly most of the projects are incomplete, leaving  homebuyer empty handed.
			
				It was argued by the  authorities before the Court in the recall application that the order passed by  the Hon’ble Court is without any jurisprudential basis for overriding the  contractual terms between the parties. If the premium for the land is paid  upfront there is no question of interest, however, if the advantage of the long  lead time for payment of the premium for the land is availed, it must be on the  basis of the agreed terms. The rate of interest was disclosed in the brochure,  in the allotment letter and in the consequential lease deed. Consequently,  amount of interest act as input and forms a part of the price payable by the  consumers. The authorities also stated that it is set jurisprudence that the  term of the contract cannot be altered without it being “arbitrary per say”  citing the case of “Central Inland Water Transportation Corporation limited  and anr. Vs Brojo Nath Ganguly and anr.”3.
  
It  was also submitted that financial loss to Greater Noida Authority in relation  to all the group housing projects would exceed Rs.4,279/- crores, while that to  the Noida Authority would be more than Rs.3,000 crores.
			
				The Hon’ble Court finally concluded in the  recall application that the Court was considering the peculiar facts only in  the case of Amrapali Group and since there was no general petition on behalf of  any or all the builder of the Noida or Greater Noida nor the scope of the  matter is wide enough, thus the relief granted was not appropriate. Further as  a result of the previous order capping rate of interest, builders are now  asking for adjustments of whatever they have paid earlier and also demanding  refund in certain cases, where amount paid is in excess. The Court concluded  that it has erred in granting relief as the impact leading to a loss of more  than INR 7000 crore to the authorities was not exactly presented before, thus  the orders in relation to capping the interest rate was recalled.
That the since the various orders passed by the  Hon’ble Supreme Court in the present Writ Petition in respect to developers  except Amrapali Group has been recalled. The State government had earlier  passed an order dated 09.06.2020 considering the widespread impact on liquidity  and cash flow due to Covid 19 pandemic. This order passed by UP Government  reducing the rate of interest is the only solace. However, the except the  limited relief provided by this order of UP Government, the terms of the  contract/allotment letter/lease deed between the developer and authorities will  be the governing document for deciding the interest to be charged and the  arrears already due to the authorities.
			
By - Devesh Bhatia
Top
