Introduction
The Supreme Court, in a recent judgment, set aside part of an arbitral  award concerning idling of manpower and machinery, attributed to delays in  completing the work beyond the stipulated period, which was passed without any  evidence and solely relied upon Hudson's formula, deeming it in conflict with  the public policy of India as contemplated under Section 34(2)(b) of the Arbitration  and Conciliation Act, 1996.
			
				Facts in a Nutshell
An arbitration was invoked by the contractor, M/s Unibros against All  India Radio, in respect of certain disputes that had arisen concerning a civil  works contract. Among various claims, there were claims for damages under  Section 73 of the Indian Contract Act made on account of delay and resultant  losses. These claims were attributable to the marked escalation in prices/rates  for the work executed beyond the stipulated contractual period, substantial  expenses associated with establishment machinery, centring, shuttering, and  other vital aspects, and thirdly, on account of loss of profit and the undue  claimant's protracted retention on the contract without any corresponding  increase in monetary benefits earned. The arbitrator rejected the claims on  account of escalation in prices and expenses associated with establishment  machinery, etc. However, the claim for damages pertaining to loss of profit was  allowed. Here, the arbitrator held that the loss of profit was worked out on a  profit allowance of 7.5 percent per annum, which, according to the arbitrator,  was reasonable in the said contract, applying the Hudson formula. Being  aggrieved by this award, the respondent challenged the award in a petition under  Section 34 of the Arbitration Act before the High Court. The High Court  remitted the matter back to the arbitrator for reconsideration, instructing the  arbitrator to pass a fresh award in respect of the claim without being  influenced by prior factors and based on the evidence available on record.  Thereafter, the arbitrator passed a fresh award, maintaining the award for loss  of profit and interest in favour of the claimant. Being aggrieved by the fresh  award passed by the arbitrator, the respondent/employer challenged the award  before the High Court under Section 34 of the Arbitration Act. The High Court,  in its order, allowed the petition under Section 34 and set aside the claim for  loss of profit, which was awarded by the arbitrator. This judgement was  challenged before the division bench of the high court under section 37 of the  arbitration act which was dismissed by the division bench. It was this decision  of the High Court that was challenged by the claimant before the Hon'ble  Supreme Court.
			
				Contentions of the Claimant
Before the Supreme Court, the claimant argued that the arbitrator's  decision was fair and well-reasoned, based on thorough examination of the  evidence. It was emphasized that the court has limited authority to interfere  with an arbitrator's award, which, under Section 34 of the 1996 Act following  the UNCITRAL Model Law, can only be set aside for specific reasons, not  modified. The claimant referenced the Supreme Court's ruling in N/S Sattyapal  Singh and Others vs. State of Gujarat to argue that a contractor is entitled to  damages for lost profit, requiring only a general assessment of damages.  Additionally, it was highlighted that Hudson's Formula is legally recognized  and widely used to calculate loss of profit, with McDermott International Inc.  vs. Burn Standard Co. Ltd. (2006) 11 SCC 181 cited to support this contention.
			
				Contentions of the Respondent
On behalf of the respondent, it was argued that in the case at hand, as  the claim was simpliciter for delay, Hudson's Formula would have no application  to award the amount of loss of profit without the aggrieved party leading any  evidence as a condition precedent for the application of the formula. The  application of Hudson's Formula hinges upon essential conditions: firstly, the  profit that the contractor must have been realistically attainable elsewhere  had he been free to leave the contract at the appropriate time; secondly, the  contractor should not have consistently underestimated his costs during  pricing, ensuring that the profit percentage was genuinely viable at that  point; thirdly, there should have been no significant changes in the market  such that work of a comparable level of profitability would have been available  to the contractor at the time of the conclusion of the contract. It was further  submitted that to fulfil these conditions satisfactorily, coherent evidence is  a sine qua non to ensure that the loss is not of a remote or imaginary nature.  It was also urged on behalf of the state that no evidence was led by the claimant,  far less any cogent evidence, to prove that there were scales of earning  surprise elsewhere by way of any other contract that was available at the time,  which it could not execute due to the prolongation of the contract. Only such  awarding of loss of profit conflicts with the public policy of India under  Section 34(2)(b) of the Arbitration and Conciliation Act, 1996.
			
				Decision of the Supreme Court
While deciding the matter, the Supreme Court relied upon the decision in  ONGC Ltd. vs. Saw Pipes Ltd. (2003) 5 SCC 705, which dealt with the  interpretation of the term "public policy of India" used in Section  34 of the Arbitration Act. It was held that the term is required to be given a  wide meaning and can be seen that the concept of public policy promotes a  matter which concerns the public good and the public interest. What is for  public or in public interest, or what would be injurious or harmful to the  public good or public interest, has varied from time to time. However, an award  which is, on the face of it, in patent violation of statutory provisions cannot  be said to be in the public interest. Such an award is likely to adversely  affect the administration of justice.
The Supreme Court held that subsequent decisions of the Supreme Court  have interpreted "public policy of India" to include arbitrariness,  non-compliance with the fundamental policy of Indian law, statutes, and  judicial precedents, the need for a judicial approach, compliance with natural  justice, manifest unreasonableness, and patent illegality. This was elucidated  in the decision of Associated Builders (2015) 3 SCC 49.
			
				The Supreme Court held that the second award was no better than the  first award, for it was equally in conflict with the public policy of India.  The Supreme Court had noted from the earlier order of the single judge of the  High Court that, while remanding the matter back to the arbitrator for  reconsideration, the arbitrator was warned not to be influenced by the factors  that weighed in his mind while making the first award. The arbitrator was  required to proceed only on the basis of evidence on record. Yet, regrettably,  the arbitrator went on to ignore the judicial decision of the High Court with  impunity. The arbitrator once again emphasized the delay caused by the respondent  in the completion of the works entrusted to the claimant by not providing  complete site and drawings within the stipulated contract period, and that  non-handing over of the site certainly constituted a fundamental breach of  contract, initiating the entire contract. He then referred to Hudson's  exposition of fundamental breach of contract, which, according to him, was the  standard text of all engineering and building contracts. It is, therefore,  apparent that the factors which weighed in the arbitrator's mind in the first  and second rounds are one and the same. To avoid any charge of being regarded  as a mirror image of the first, the second award appears to have been expressed  in language somewhat different from the earlier ones, without, however, there being  any change in substance.
The Supreme Court further referred to the judgment of the Hon'ble  Supreme Court in Bharat Coking Coal (2004) 5 SCC 109, where the Hon'ble Supreme  Court had held that it is not unusual for contractors to claim loss of profit arising  out of diminution of turnover on account of delay in the matter of completion  of the work. What needs to be established in such a situation is that, had the  contractor received the amount due under the contract, he should have utilized  the same for some other business in which he could have earned profit. Unless  such a basis is reasonably established, a claim for loss of profits could not  have been granted. In this case, no such material was available on record. In  the absence of any such evidence, the arbitrator could not have awarded the  same.
			
				The Supreme Court held that to support a claim for loss of profit  arising from a contract delay or missed opportunities from other available  contracts that the claimant could have earned elsewhere by undertaking, it  becomes imperative for the claimant to substantiate the presence of a viable  opportunity through compelling evidence. This evidence should convincingly  demonstrate that, had the contract been executed promptly, the contractor could  have secured supplementary profits utilizing its existing resources elsewhere.  The Supreme Court further held that Hudson's Formula, while having attained  acceptability and being well understood in the trade, does not, however, apply  in a vacuum. Hudson's Formula, as well as other methods used to calculate  claims for loss of off-site overheads and profit, do not directly measure the  contractor's exact costs. Instead, they provide an estimate of the losses the  contractor may have suffered. While these formulae are helpful, they can only  support the contractor's claim for loss of profit if the contractor has shown,  with evidence, the loss of profit and opportunities it suffered owing to the  prolongation.
The Supreme Court therefore held that the arbitral award in question, was  patently illegal in that it was based on no evidence and was, thus, outrightly  perverse; therefore, again, it is in conflict with the "public policy of  India" as contemplated by section 34(2)(b) of the Act.1
			
By - Chaitanyaa Bhandarkar
Top
